REBUILD OF LIFT STATION #3A INFORMATION

5/17/2021

The bypass pumping has been completed and the lift station is currently operating with new sewage pumps.  The new generator will be in operation this week.  

05/07/21

The contractor is currently constructing the access path to lift station 3A.   Electrical work is still ongoing for the project.

04/04/21

Sewage pumps and electrical services throughout the lift station are currently being installed by the contractor.  They are also working on the initial site grading.

03/18/21

The contractor is installing gravity sewer at the lift station as well as working on miscellaneous piping involved in construction of the concrete vault.

01/21/21

The contractor should be on site today to install piping for the lift station.

01/07/21

The vault is approximately 85% complete.  Contractors will be working on the vault hatch in the coming week as well as backfilling around the vault area.

12/04/2020

Contractors will be constructing the new concrete vault for the next 2 to 3 weeks.

11/30/20

Excavating for the new concrete vault for the lift station has begun.

11/23/20

The rebuild of Lift Station #3A will begin November 30, 2020.  We will keep residents informed as additional information becomes available.